Cap Project Update: 1/16/26

2023 Capital Improvement Project
I’m pleased to share that our contractors have completed the installation of the new double shades for the recently replaced windows at the High School, adding both comfort and energy efficiency to our learning spaces. In addition, work continues to progress on the upgraded security systems throughout the district. We appreciate everyone’s patience and support as these important improvements move forward.
Mexico High School
- Masonry Contractor removed the heat tent for the front steps.

- Window Blind Contractor worked on installing window blinds.
This photo shows the light filtering shades lowered:

- This photo shows the room darkening shades lowered:

- This photo shows both shades raised:

- Day Automation Continues to work throughout the district working on Security Switch over, camera systems, camera mapping, door access control throughout the school district. This system is not operational until Day Automation has done their final testing and offered training to the District.
-
Next Steps
Middle School
- Site Stairs and railings
- Benches
- Window Replacement
-
High School
- Attic HVAC replacement
- Masonry Restoration
- Window Replacement
- Pedestrian Bridge Replacement
- Testing of lockdown devices and strobes
-
Mexico Elementary
- Masonry Restoration
- Window Replacements
- Testing of lockdown devices and strobes
-
New Haven Elementary
- Window Replacements
- Testing of lockdown devices and strobes
-
Palermo Elementary
- Masonry Restoration
- Window Replacements
- Testing of lockdown devices and strobes