December 15, 2025
Cap Project Update: 12/15/25

2023 Capital Improvement Project
Update December 15, 2025
Mexico High School
- Installing emergency notification clocks at various locations
- Contractor Removing Windows (Main Office)
- Contractor Removing Windows (G4 Home Ec)


- Contractor Installing Windows (Room G4 Home Ec)


- Working on Lockdown/ Lockout Controls as well as testing the system
- Electrical contractor worked at connecting the wiring in the clock tower
- Masonry contractor received the new stone for the front entrance steps
- Masonry contractor has finished setting up the winter enclosure

- Masonry contractor has finished setting up the winter enclosure
- Contractor Removing Windows (G4 Home Ec)
-
Day Automation continues to work throughout the district with door controls, and the lockout/ lockdown system that includes programing.
Next Steps
Middle School
- Site Stairs and railings
- Benches
- Window Replacement
- Testing of lockdown devices and strobes
-
High School
- Attic HVAC replacement
- Masonry Restoration
- Window Replacement
- Electrical connection of tower clock system
- Window shades to be installed
- Testing of Lockdown devices and strobe
-
Mexico Elementary
- Masonry Restoration
- Window Replacements
-
Testing of lockdown devices and strobes
New Haven Elementary
- Window Replacements
- Testing of lockdown devices and strobes
-
Palermo Elementary
- Masonry Restoration
- Window Replacements
- Testing of lockdown devices and strobes
-