Cap Project Update: 12/5/25

Dear MACS Family and Community,
Our contractors are wrapping up Phase 1 of the High School window replacement project. Phase 2, which includes all district buildings, is scheduled for completion during the spring and summer of 2026. Window treatments for the High School have been ordered and will be installed as soon as they arrive. In addition, our masons will soon finish the stone replacement at the front of the High School.
You may notice flashing lights outside some buildings as contractors test the newly installed emergency notification systems. These exterior lights are designed to signal emergency events—such as a lockout or lockdown—indicating that people should not enter the building. We will share more details once these systems are fully operational.
I also encourage you to come out and vote on the 2025 Capital Improvement Project on Wednesday, December 10, from 12:00 p.m. to 9:00 p.m. in the Middle School Gym. If approved, this project will be implemented at no additional cost to taxpayers.
If you have any questions, please feel free to reach out to Jolean Bliss, Business Executive, or to me directly.
Thank you for your continued support of MACS!
Dr. Runner, Superintendent
2023 Capital Improvement Project
Mexico High School
- Installing emergency clocks at various locations
- Contractor Removing Windows (Main Office)
- Contractor Removing Windows (105)

- Contractor Removing Windows (104)

- Contractor Removing Windows (103)

- Contractor Installing Windows (Room 219)

- Contractor Installing Windows (220)

- Contractor installing Windows (Main Office)

- Contractor installing Windows (Room 105)

- Contractor installing Windows (Room 104)

- Contractor installing Windows (Room 103)

- Working on Lockdown/ Lockout Controls as well as testing the system
- Masonry Contractor received the new stone for the front entrance steps.
- Masonry contractor has started to set up the winter enclosure to heat the work area.

Mexico Elementary School
- Masonry contractor has started to set up the winter enclosure to heat the work area.
- Contractor Removing Windows (105)
- Installing new brick at the brick locations to be repaired.
-
Day Automation Continues to work throughout the district with door controls, Lockout/ lockdown system that includes programing.
-
Next Steps
Middle School
- Site Stairs and railings
- Benches
- Window Replacement
- Testing of Lockdown devices and strobes
-
High School
- Attic HVAC replacement
- Masonry Restoration
- Window Replacement
- Electrical connection of tower clock system
- Window shades to be installed
- Testing of Lockdown devices and strobes
-
Mexico Elementary
- Masonry Restoration
- Window Replacements
- Testing of Lockdown devices and strobes
-
New Haven Elementary
- Window Replacements
- Testing of Lockdown devices and strobes
-
Palermo Elementary
- Masonry Restoration
- Window Replacements
- Testing of Lockdown devices and strobes