Cap Project Update: 11/7/25

Dear MACS Family and Community,
I’m pleased to share an update on the progress of our 2023 Capital Project. Phase 1of the window replacement is nearing completion at the High School, marking an exciting milestone in our commitment to improving learning environments across the district. Looking ahead, we want to remind families and staff that window replacements for all buildings are scheduled for the summer of 2026. Air handlers for the High School have a late December anticipated delivery date. These upgrades are part of our continued efforts to enhance energy efficiency, safety, and comfort for our students and staff.
Sincerely,
Dr. Runner, Superintendent
Mexico High School
- Installing lockdown/lockout wiring
- Contractor Removing Windows (Room 50)

- Contractor Removing Windows (50B)

- Contractor Removing Windows (126)

- Contractor removing Windows (room207)

- Contractor Installing Windows (Room 50)

- Contractor Installing Windows (Room 50C)

- Contractor installing Windows (Room 50)

- Work Continued on the trim pieces at roofs L&M as well as the final roofing around the new roof hatches
- Repointing masonry



Mexico Middle School
- Installation of the gate arms

Next Steps
Middle School
- Site Stairs and railings
- Benches
- Window Replacement
High School
- Attic HVAC replacement
- Masonry Restoration
- Window Replacement
- Installation of tower clock system
Mexico Elementary
- Masonry Restoration
- Window Replacements
New Haven Elementary
- Window Replacements
Palermo Elementary
- Masonry Restoration
- Window Replacements