August 1, 2025
Cap Project Update: 8/1/25

Dear MACS Family and Community,
Our Capital Improvement Project work continues, with contractors diligently putting in the hours to complete the work on schedule. Please note the photos showing progress from this past week! Dr. Runner
2023 Capital Improvement Project
Mexico High School
- Masonry grinding out of the joints for repointing
Mexico Middle School
- Installation of storm structures outlet. (Storm water outlets and piping is nearly complete in the upper section.)
- Continuing of the stone base at parking lot
- Continuing the Installation of light pole bases
- Excavating for electrical conduit for the light pole bases
- Running conduit to the light Pole bases
- Backfilling electrical conduit trenches
- Started pulling wire through the conduits from pole base to pole base
·
These stairs will connect the upper loop to the lower loop on the hill next to the District Office.
- Installation of the foundation for the stairs
Mexico Elementary School
- Roofing tear off continues
- West side of the roof ready for Membrane
Palermo Elementary School
- Removal of the masonry above where the lintel will be replaced
New Haven Elementary School
- Fascia Replacement and caulking
Brick Replacement on the front of the building (installing Underlayment)
- Brick repointing in the courtyard
Next Steps
- Middle School
- Parking lot base and binder
- Rear Parking lot demolition
- Stormwater detention pond
- Curbing and sidewalks
- Stairs
- High School
- Attic HVAC replacement
- Masonry Restoration
- Window Replacement
- Mexico Elementary
- Masonry Restoration
- New Haven Elementary
- Masonry Restoration
- Palermo Elementary
- Masonry Restoration