Cap Project Update: 6/27/25

2023 Capital Improvement Project Work
Mexico High School
- Extending the Catwalks are near completion in the Attic to accept the new Air Handler Units
- Piping of the of the Condensate Tank ready for controls to be connected
Mexico Middle School
- Installing sub base in the lower portion of the Parent Drop off Triangle
- Installing the Dry Stormwater management pond
- Excavation for the new waterline.
- Installing new waterline for the new service in the basement
Mexico Elementary School
- No Work this week
Palermo Elementary School
- No work this week
New Haven Elementary School
- No Work this week
Next Steps
- Middle School
- Parent drop off site work to continue
- Rear parking lot demolition and storm retention structures
- Waterline Service/RPZ installation (Switch over of the new waterline service.)
- High School
- Attic HVAC replacement
- Masonry Restoration
- Window Replacement
- Mexico Elementary
- Masonry Restoration
- Roofing Replacement
- New Haven Elementary
- Masonry Restoration
- Eave trim replacement
- Palermo Elementary
- Masonry Restoration
- Lintel replacement