Capital Improvement Project Update May 23, 2025

  • The storage and office trailers were brought into the Staging Area at the High School.

A two containers in a parking lotAI-generated content may be incorrect.

  •  Temporary power was run to the office trailer.

A parking lot with a red car parked next to a green fieldAI-generated content may be incorrect.

 

 

 

 

  • The remainder of the Construction Area Fencing was set up at the Middle School parent drop off triangle.

 A road with a fence and treesAI-generated content may be incorrect.

  • The demolition of the parent drop off started by removing the trees.

A fenced off area with a construction site in the backgroundAI-generated content may be incorrect.

 

 

 

 

 

 

 

Next Steps

Middle School

        • Parent drop off site preparation and tree removal
        • Rough Grading and storm structure installation
        • Rear parking lot demolition and storm retention structures

High School 

        • Catwalk extension installation
        • New Roof Hatch installation
        • Condensate removal and replacement
        • Attic HVAC replacement
        • Masonry Restoration
        • Window Replacement

Mexico Elementary

        • Masonry Restoration
        • Roofing replacement

New Haven Elementary

        • Masonry Restoration
        • Eave trim replacement